Subject: 19046/Chg Order 7(Final)/CD-1-88/Talley Construction Date: Mon, 12 Feb 1990 11:19:00 -0500 RESOLUTION NO. 19046 A RESOLUTION AUTHORIZING CHANGE ORDER NO. 7 (FINAL), CONTRACT NO. CD-1-88, WAUHATCHIE PIKE REHABILITATION, WITH TALLEY CONSTRUCTION COMPANY, TO ACCEPT SAID PROJECT AS COMPLETE AND TO DECREASE THE CONTRACT IN THE AMOUNT OF TWELVE THOUSAND FOUR HUNDRED NINETY-SEVEN AND 35/100 DOLLARS ($12,497.35) FOR A TOTAL CONTRACT AMOUNT OF TWO MILLION FOUR HUNDRED EIGHTY-NINE THOUSAND NINE HUNDRED NINETEEN AND 63/100 DOLLARS ($2,489,919.63), AND TO INCREASE THE CONTRACT COMPLETION TIME BY TWO HUNDRED FIFTY-SEVEN (257) DAYS FOR A TOTAL OF NINE HUNDRED EIGHTY-SEVEN (987) DAYS. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA, TENNESSEE, That there be and is hereby authorized Change Order No. 7 (Final), Contract No. CD-1-88, Wauhatchie Pike Rehabilitation, with Talley Construction Company, to accept said project as complete and to decrease the contract in the amount of $12,497.35 for a total contract amount of $2,489,919.63, and to increase the contract completion time by 257 days for a total of 987 days. ADOPTED: June 4, 1991 :cjc